19.78.030 Application requirements.
A. All activity to which this chapter applies requires an application and permit consistent with this chapter. A separate permit is not required if an application has been approved for a building permit, preliminary plat, or a final planned unit development.
B. Applications must be on forms provided by the department and must include:
1. A site plan showing location, type, and size of existing significant trees and native vegetation; designation of clearing limits; and other requirements identified by the director;
2. If excavated material is to be wasted off-site, a description of the location and the route to the disposal site;
3. Demonstration of compliance with AMC Chapter 19.76, Stormwater Management;
4. A construction site sediment transport potential worksheet which will guide city staff on the need for a site inspection prior to permit issuance. (Ord. 2991 § 1 (Att. A), 2016)