The time frame for review of an application for a master permit or a construction permit begins to run when an application is submitted, not when the application is deemed complete. The time frame for submitting and reviewing master permits and construction permits is the same, unless otherwise specified.

Colocating Wireless Facilities

Colocating Small Wireless Facility

New Small Wireless Facility

New Wireless Facilities

Construction Permit – All Wireless Facilities

Master Permit Renewal – All Wireless Facilities

Application submission

Master use and construction permit applications should each be submitted 90 days prior to planned use.

Master use and construction permit applications should each be submitted 60 days prior to planned use.

Master use and construction permit applications should each be submitted 90 days prior to planned use.

Master use and construction permit applications should each be submitted at least 120 days prior to planned use.

Applications for complex projects should be submitted at least 60 days prior to the planned use, and in no case less than 30 days prior to the planned use.

A permittee may submit an application for renewal no more than 180 days and no less than 120 days before expiration of the current master permit.

Time frame for decision (from receipt of complete application)

Written decision due within 90 days.

Written decision due within 60 days.

Written decision due within 90 days.

Written decision due within 120 days.

City Engineer must act within a reasonable time, generally not to exceed 30 days, and in no case can he or she exceed the time frames for review set forth in this table.

Written decision due within 90 days.

(Ord. 3039 § 2, 2019)