The time frame for review of an application for a wireless facility permit or wireless conditional use permit begins to run when an application is submitted, not when the application is deemed complete.

Modifications that Are Not Substantial

Colocating Wireless Facilities

New Wireless Facility

Colocating Small Wireless Facilities

New Small Wireless Facility

Time Frame

Approval required within 60 days from receipt of submission of application.

Written decision due within 90 days from submission of application.

Written decision due within 150 days from submission of application.

Written decision due within 60 days from submission of application.

Written decision due within 90 days from submission of application.

Notes

If the city finds that the application involves a substantial change, the city may process the application as one for a new facility or deny the application.

This provision does not apply to small wireless facilities.

This provision does not apply to small wireless facilities.