A. When Required. A notice of application is required when shown in AMC 19.20.030, Types of review.

B. Contents. The notice of application must include all of the following:

1. The application number.

2. The name of the applicant.

3. The date of application, the date of the notice of completion for the application, and the date of the notice of application.

4. Identification of the location of the project, by address if available.

5. A description of the proposed application, a list of the project permits included in the application and, if applicable, a list of any studies requested under RCW 36.70B.070.

6. The identification of other permits not included in the application, to the extent known by the city.

7. The identification of existing environmental documents that evaluate the proposed project and, if not otherwise stated on the document providing notice of application, the location where the application and any studies can be reviewed.

8. A statement of the public comment period, which lasts the number of days specified for the application type in AMC 19.20.030, Types of review; except all shoreline permits subject to the comment period as outlined in WAC 173-27-110(2)(e), which allows for a 30-day comment period.

9. A statement of the right of any person to comment on the application, receive notice of and participate in any hearings, request a copy of the decision once made, and any appeal rights.

10. The date, time, place and type of hearing, if applicable, and scheduled at the date of notice of the application.

11. A statement of the preliminary determination of consistency, if one has been made at the time of notice, and of those development regulations that will be used for project mitigation and consistency.

12. If the city is using the optional DNS process (WAC 197-11-355), additional information will be added to the notice as required by WAC 197-11-355(2).

13. Any other information determined necessary by the city, such as the city’s likely threshold determination, if complete at the time of issuance of the notice of application.

C. Timing.

1. The Department must distribute a notice of application within 14 days of determination that an application is complete and at least 15 days prior to any open record hearing.

2. Within seven days after the end of the public comment period, the Department must transmit to the applicant a copy of public comments timely received in response to the notice of application, together with a statement that the applicant may submit a written response to these comments within seven days from the date the comments are transmitted. (Ord. 3040 § 2 (Att. A), 2019; Ord. 2992 § 1 (Att. A), 2016. Formerly 19.20.140)